A special Region 9 Board of Education meeting was held in June about a technical error that is delaying the roof restoration project at Joel Barlow High School. There was a problem with the public notification. The referendum date was set at a meeting four days after notice was given of the meeting, not five days as required.
The $1.4 million project would have started in late July, but has been pushed back to August.
The Region 9 district is holding a referendum tomorrow.